Council Requirements for Site Cuts on the Fraser Coast: What Needs Approval

Table of contents

Site cut and fill earthworks on a Fraser Coast building block

Most people find out whether their site cut needs council approval the expensive way: after the machine has been and someone complains. On the Fraser Coast the rules are clearer than people expect. Whether you need an application comes down mainly to how much material moves, how high the cut or fill gets and how close it sits to your boundary.

This guide covers the requirements in the Fraser Coast Regional Council area, which includes Hervey Bay, Maryborough and the surrounding towns. It is based on the current Fraser Coast Planning Scheme. It is a practical summary rather than legal advice, so always confirm your own block with council or your certifier before you dig.

When does a site cut need council approval?

Under the Fraser Coast Planning Scheme, cutting or filling land is “operational work”. Whether it needs a development application depends mostly on the volume of material involved:

  • Up to 100 cubic metres of cut or fill on most urban and residential land is accepted development subject to requirements. You do not lodge an application, but the work has to meet the requirements set out in council’s Works, services and infrastructure code.
  • More than 100 cubic metres generally needs code assessment, which means an operational works application and approval before work starts.
  • In the Rural zone the trigger is 500 cubic metres instead of 100, unless the earthworks are associated with a rural activity, in which case they are generally accepted development.

To put 100 cubic metres in perspective, cutting a 20 metre by 10 metre house pad down by half a metre moves exactly 100 cubic metres. Plenty of ordinary residential pads sit right on that line, which is why it is worth measuring before you assume you are under it.

The limits a small site cut still has to meet

Staying under the volume threshold does not mean anything goes. To be accepted development without an application, a cut or fill on the Fraser Coast generally has to meet these requirements from the Works, services and infrastructure code:

  • Height change: no more than 1.0 metre of cut or fill relative to natural ground at any point on sites with a slope under 15%, or 1.5 metres on sites with a slope of 15% or more and in the Rural zone.
  • Boundary setback: no part of a cut or fill batter within 1.5 metres of a property boundary, unless the level change is less than 200mm and no vegetation needs removing.
  • Retaining walls: no higher than 1.5 metres.
  • Stockpiles: kept wholly on site, in a single area no bigger than 50 square metres and at least 10 metres from any boundary.
  • Stability: batters and walls structurally adequate, and earthworks carried out to AS 3798, the Australian guideline for earthworks on commercial and residential developments.
  • Drainage: the work must not block or redirect overland stormwater flow, and must not use contaminated or waste material as fill.

If your job cannot meet those requirements, for example a cut deeper than 1 metre on a flat block, it generally becomes assessable and needs an application even if the volume is small.

Retaining walls are building work, not earthworks

This catches a lot of people out. Under the planning scheme, a retaining wall is treated as building work under the Building Act, not as operational work. So the earthworks and the wall can need two different approvals from two different people.

In Queensland a retaining wall can generally be built without building approval only if it is no more than 1 metre high including the soil it retains, is at least 1.5 metres from a building or another retaining wall, has no surcharge loading such as a driveway or footing within its zone of influence and is structurally adequate. Anything outside that needs building approval, usually through a private building certifier, and often an engineer’s design.

Read the two rules together and the practical limit for most flat Fraser Coast blocks is clear: keep cuts to 1 metre or less and keep walls under 1 metre, or plan on getting approvals.

Six things that bring extra scrutiny to a Fraser Coast site cut

How the approval categories compare

CategoryWhat it meansTypical site cut example
AcceptedNo application and no code requirements to meetEarthworks on a rural property for a rural activity
Accepted subject to requirementsNo application, but the work must meet the code requirementsA small house pad under 100 m³ with under 1 m of cut
Code assessmentOperational works application and approval before startingA larger pad, bulk fill or anything over 100 m³ on residential land

Overlays can change these categories. Flood hazard, coastal, bushfire and environmental overlays in the scheme can make work assessable that would otherwise be accepted, so check the overlay mapping for your lot before relying on the volume alone.

The cheapest site cut is the one that only gets done once. Ten minutes on the planning scheme before the machine arrives saves weeks of putting it back.

What an operational works application usually needs

ItemWhy council asks for it
Engineering drawingsShow existing and proposed levels, batters and volumes
Erosion and sediment control planShows how soil stays on site during works
Stormwater and drainage detailsShows the work does not worsen flows onto neighbours or the street
Retaining wall designWhere walls are involved, often certified by an engineer
Fill source and testingConfirms fill is clean and compacted to specification
Subsoil drainage being installed during site preparation

Flood, stormwater and your neighbours

Whatever the category, council’s code requires that earthworks do not change flood flows, velocities or levels outside your site and do not interfere with overland flow. Filling a low block can push water onto the neighbours, and that is the most common source of earthworks complaints. Fraser Coast flood mapping has been updated in recent years, so check the current flood hazard overlay for your lot rather than relying on what applied when you bought it.

Erosion and sediment control applies to every job, approved or not. A bare cut site after a coastal storm sends sediment straight into the street drains. Our 12 step site preparation checklist covers where sediment control fits in the order of works.

Four common Fraser Coast scenarios

Frequently asked questions

Not always. On most residential land, cut or fill of up to 100 cubic metres is accepted development if it meets council’s code requirements, including no more than 1 metre of height change on a flat block. Above 100 cubic metres, or where you cannot meet those requirements, you generally need an operational works application.

Up to 100 cubic metres on most urban and residential land, or 500 cubic metres in the Rural zone where the work is not for a rural activity, provided the work meets the code requirements. Overlays such as flood hazard areas can change this.

On sites with a slope under 15%, the code requirement is no more than 1.0 metre of cut or fill relative to natural ground. On sites with 15% slope or more, or in the Rural zone, the limit is 1.5 metres.

In Queensland a retaining wall generally needs building approval unless it is 1 metre high or less, at least 1.5 metres from a building or another retaining wall and has no surcharge loading. Retaining walls are building work, separate from the earthworks approval.

No. Gympie and Bundaberg have their own councils and planning schemes with different thresholds. This guide covers the Fraser Coast Regional Council area only. See our Gympie and Bundaberg earthworks pages for those areas.

A good contractor will flag the likely triggers when quoting, such as volume, depth, walls and flood mapping. The final answer comes from council or your certifier, so check before work starts.